Case Study 3 - Detailed Design

The expansion of an existing facility by means of the addition of a series of new therapeutic protein purification suites. The main objective of the design was to account for the phased expansion of the facility, from 10 kg/yr of a single product in one suite, through to 400kg/yr of two products in four suites.

Aims & Objectives

  • Minimise capital & redundancy during expansion
  • Minimise headcount
  • Determine buffer prep and hold requirements
  • Provide data for utility distribution design
  • Determine connectivity / material transfer requirements
  • Demonstrate concept to end-client

Results

  • Detailed expansion plan:
    • Utility demand profiles for each header
    • Buffer hold and prep vessel requirements
    • Minimal buffer prep & hold redundancy
  • Potential bottlenecks at full production:
    • 5% WFI unavailability
    • 90% WFI still peak utilisation
  • Space restrictions at full production:
    • Insufficient parts washer/autoclave provision
    • Utilisation >90%
    • Queues >24hr